Fixed SPST size and generated new Gerbers
by
Wesley L.
6 years 7 months
Fixed Click signal and made new gerbers
Click signals from the low level systems are now tied together.
by
Wesley L.
6 years 7 months
Updated png image of the v3 HL board
by
Wesley L.
6 years 7 months
Moved files around
Current PCB files are moved one level up
by
Wesley L.
6 years 7 months
breakout holes
Fixed hole size for the breakout boards. Should be 3mm for all
by
guantamanera
6 years 7 months
Added Board and fixed Test Points
Added the BRD file and fixed GPS test points and added test points for Raspberry UART
by
Wesley L.
6 years 7 months
changes
Changed DPDT. Updated with new Due library where the silk screen has been moved.
Solved drill hole issue with Due library
by
guantamanera
6 years 7 months
Removed second Compass
by
Wesley L.
6 years 7 months
Added correct RJ45 footprints
by
Wesley L.
6 years 7 months
- 1 of 100
- ››