lib 3
by Benkess 9 months 2 weeks
lib 2
by Benkess 9 months 2 weeks
motor updates step 1/2
by Benkess 9 months 2 weeks
Rules Checking and BOM
by Troy Harmon 9 months 2 weeks
Finished Initial Routing and Checks
by Troy Harmon 9 months 2 weeks
Completed some power pathing traces
by Troy Harmon 9 months 3 weeks
Fixed footprints and started on layout
by Troy Harmon 9 months 4 weeks
Switched out motor parts for HI duplicates.
by Troy Harmon 10 months 1 day
Added debugging connectors and finished up new ana...
by Troy Harmon 10 months 1 week
Added debugging connectors and finished up new analog power inputs.
changed the directory set up
by Nitya Khamar 1 year 6 days