added in no connection flags, all DRC and ERC tests passed
by
NK22
3 weeks 4 days
added power flag to pass ERC
by
NK22
3 weeks 4 days
routed all the traces between the connectors
by
NK22
3 weeks 4 days
fixed labels schematic
by
Anusha Devisetty
3 weeks 4 days
added db9 footprints and updated schematic to fix traces
by
Anusha Devisetty
3 weeks 4 days
looked into files
by
Anusha Devisetty
2 months 2 hours
finished schematic and named wires
by
Anusha Devisetty
2 months 4 hours
created pcb and added CAN connection
by
Anusha Devisetty
2 months 6 hours
added all connectors except CAN
by
Anusha Devisetty
2 months 7 hours
added files for motor distribution board
by
Anusha Devisetty
2 months 2 weeks