initial drc review done
by darrenawinter 10 months 1 week
finished layout must do design rules to adhere for...
by darrenawinter 10 months 1 week
finished layout must do design rules to adhere for polygons and stitching
poured copper, requires additional nets to connect
by darrenawinter 10 months 1 week
initial routing finished
by darrenawinter 10 months 1 week
began microcontroller layout
by darrenawinter 10 months 1 week
updated layout
by Darren Winter 10 months 1 week
placed and combined components
by Darren Winter 10 months 2 weeks
Updated PCB for microcontroller
by Darren Winter 10 months 2 weeks
Continued lay out and done for scehamtics 2 - 4
by Darren Winter 11 months 1 week
further layout on power-usb, need to check routing...
by Darren Winter 1 year 1 week
further layout on power-usb, need to check routing and pins