hw: address review comments, move to pre-r0.1
by Kate Temkin 5 years 7 months
rev0: get most of the major routing done
by Kate Temkin 5 years 9 months
rev0: get most of the major routing done

still needs power routing, length matching for the busses,
and routing for the misc control stuff
rev0: more routing scaffolding
by Kate Temkin 5 years 9 months
rev0: throw the parts down so we can get starting ...
by Kate Temkin 5 years 9 months
rev0: throw the parts down so we can get starting routing
rev0: clean up library references and backup files
by Kate Temkin 5 years 9 months
rev0: finish capture and start routing (woo!)
by Kate Temkin 5 years 9 months
schematic: finish initial capture
by Kate Temkin 5 years 9 months
Report a bug